Ground broken for new fire station

Staff writer

Despite gloomy weather, dozens gathered Saturday as ground was broken for a new fire station at Ash and 3rd Sts. in Hillsboro.

The roughly 16,000-square-foot building will replace the department’s current station at city hall. Construction is expected to cost about $4.5 million, paid for out of a $5.4 million bond the city was authorized to use.

For Mayor Lou Thurston, the project has been nearly a decade in the making. For former fire chief Ben Steketee, the need for a larger station became apparent 16 years ago, when the department entered into an agreement with Marion County Emergency Medical Services.

At times, the department has had to store vehicles at the former AMPI, creating a half-mile gap between some of its apparatuses.

Today, Hillsboro fire department has nine vehicles to house.

“That arrangement has never been ideal,” Steketee said. “Having to retrieve an apparatus from another building before responding to an emergency creates unnecessary delays. Unfortunately, that challenge still exists today.”

The new fire station will feature an 80-by-120-foot engine bay, allowing six of the department’s vehicles to be deployed at once. An attached, two-story administration building will measure 80 by 80 feet and include training, storage, and locker rooms.

It also will serve as a storm shelter.

The administration building’s second floor will be left unfinished, giving Hillsboro and the fire department time to determine how best to use the additional space.

The site will include a parking lot with room for roughly 40 vehicles, NF Construction owner Cody Nelson said. The east side of the building will be “constructed so that it’s expandable for future growth.”

Much of the work will be kept close to home.

Hillsboro contracted with NF Construction and EBH Engineering, both of Marion, for building and civil engineering work. The city also hired Kaw Valley Engineering, which has multiple offices across Kansas, for structural engineering, along with Deam and Deam Architecture of Junction City.

The decision to work with local contractors and suppliers was intentional.

“When local people build local projects, the investments stay in the community,” Nelson said. “And the people building this station take pride in it because it serves their own neighbors.”

Construction is expected to be completed by late summer or early fall.

“One day, hopefully not too far down the road,” Thurston said, “we’re going to gather again to open the doors of this new fire station … and when we do, I hope we’ll remember that what we’re beginning here today isn’t simply a construction project — it’s a promise, a promise to those who serve, a promise to those who depend on them, and a promise to the future generations that will follow us.”

Last modified Nov. 5, 2026

 